Kuala Lumpur
Project Name: Espland Residences Bukit Jalil
S&P Date: 15/08/2008
Completion Date: 15/08/2010
Actual Progress Stage: 73%
Developer: Setia Putrajaya Development Sdn Bhd
Project Name: Park Village Condominium
S&P Date: 29/12/2009
Completion Date: 29/12/2012
Actual Progress Stage: 3%
Developer: Amatir Resources Sdn Bhd
Project Name: Seni Mont Kiara
S&P Date: 25/09/2007
Completion Date: 25/09/2010
Actual Progress Stage: 75%
Developer: E C H Development & Management Sdn Bhd
Project Name: 2974 & 2975 (Wilayah Persekutuan KL)
S&P Date: 24/08/2007
Completion Date: 24/08/2010
Actual Progress Stage: 87%
Developer: Noble Paradise Sdn Bhd
Project Name: Taman Pinggiran Pelangi Fasa 2 (Wilayah Persekutuan KL)
S&P Date: 17/11/2008
Completion Date: 17/11/2010
Actual Progress Stage: 47%
Developer: Prinaissance Development Sdn Bhd
Project Name: Lot 64 Seksyen 89A (Wilayah Persekutuan KL)
S&P Date: 10/10/2007
Completion Date: 10/10/2010
Actual Progress Stage: 75%
Developer: Primaworld Embassyview Sdn Bhd
Project Name: Brunsfield Embassyview (Wilayah Persekutuan KL)
S&P Date: 17/03/2008
Completion Date: 17/03/2011
Actual Progress Stage: 65%
Developer: Panareno Sdn Bhd
Project Name: PT7560 (Wilayah Persekutuan Putrajaya)
S&P Date: 14/12/2007
Completion Date: 14/12/2010
Actual Progress Stage: 68%
Developer: Sentul Perdana Sdn Bhd
Project Name: 1 Sentul (Wilayah Persekutuan KL)
S&P Date: 25/01/2008
Completion Date: 25/01/2011
Actual Progress Stage: 62%
Developer: Promatik Emas Sdn Bhd
Project Name: Panorama (Wilayah Persekutuan KL)
S&P Date: 02/04/2008
Completion Date: 02/04/2011
Actual Progress Stage: 65%
Developer: KL Landmark Sdn Bhd
Project Name: Regent Residence
S&P Date: 03/09/2008
Completion Date: 03/09/2011
Actual Progress Stage: 37%
Developer: Amarin Wickham Sdn Bhd
Project Name: Amarin Wickham Sdn Bhd
S&P Date: 30/11/2009
Completion Date: 30/11/2012
Actual Progress Stage: 2%
Source: Ministry of Housing and Local Government (Kementerian Perumahan Dan Kerajaan Tempatan)
Selangor State Zone 3 (Shah Alam, Sabar Bernam, Kuala Selangor, Kapar, Meru, Paya Jaras, Kuala Langat, Sepang, Dengkil, Banting)
Project Name: Avira (BR13D) Klang
S&P Date: 06/02/2009
Completion Date: 06/02/2011
Actual Progress Stage: 2%
Developer: Sime UEP Development Sdn Bhd
Project Name: Bandar Bukit Raja Fasa 14A Klang
S&P Date: 18/04/2009
Completion Date: 18/04/2011
Actual Progress Stage: 4.90%
Developer: Rumpun Ehsan Sdn Bhd
Project Name: Lot 133 Sepang, Selangor
S&P Date: 14/10/2008
Completion Date: 14/10/10
Actual Progress Stage: 49.25%
Developer: Jatidiri Gigih Sdn Bhd
Project Name: Bandar Saujana Putra Kuala Langat, Selangor
S&P Date: 25/07/2009
Completion Date: 25/07/2011
Actual Progress Stage: 0%
Developer: Gabungan Efektif Sdn Bhd
Project Name: Bandar Parklands Fasa b11 Klang
S&P Date: 25/06/2008
Completion Date: 25/06/2010
Actual Progress Stage: 67.95%
Developer: Detik Jitu Sdn Bhd
Project Name: Lot 511 Sepang, Selangor
S&P Date: 14/08/2009
Completion Date: 14/08/2011
Actual Progress Stage: 5%
Developer: Segar Timor Sdn Bhd
Project Name: Desa Saujana Putra Sepang, Selangor
S&P Date: 10/08/2009
Completion Date: 10/08/2010
Actual Progress Stage: 5%
Developer: Raffles Villa Sdn Bhd
Project Name: Istana Villas Klang
S&P Date: 09/08/2009
Completion Date: 09/08/2011
Actual Progress Stage: 5%
Source: Ministry of Housing and Local Government (Kementerian Perumahan Dan Kerajaan Tempatan)
Selangor State Zone 2 (Hulu Selangor, Gombak, Hulu Langat, Ampang, Kajang, Cheras, Bangi, Semenyih, Rawang, Batu Caves, Selayang, Ulu Klang, Melawati, Serdang, Balakong, Lembah Jaya, Ampang Jaya)
Project Name: Saujana Rawang Fasa 6, Gombak
S&P Date: 28/08/2009
Completion Date: 28/08/2011
Actual Progress Stage: 0%
Developer: Esatek Sdn Bhd
Project Name: Seksyen 15, Bandar Baru Bangi, Hulu Langat
S&P Date: 29/07/08
Completion Date: 29/07/10
Actual Progress Stage: 44.5%
Developer: Newteque Sdn Bhd
Project Name: Apartment Impian, Gombak
S&P Date: 04/10/07
Completion Date: 04/10/10
Actual Progress Stage: 47.08%
Developer: Bina Satu Leasing Sdn Bhd
Project Name: Taman Serendah Makmur (Hulu Selangor)
S&P Date: 1/7/2008
Completion Date: 1/7/2010
Actual Progress Stage: 55%
Source: Ministry of Housing and Local Government (Kementerian Perumahan Dan Kerajaan Tempatan)